9 April 2015
In recent weeks we have again been working on several things in parallel. In the workshop, Ernst has been cleaning two sections that we previously removed from the trailing-edge strip of the centre section. Each of these sections has two hatches down into storage compartments. Thanks to an incredible ability to get his hands and fingers into the most inaccessible places, he has managed to open and remove these hatches.

Out in the concrete hall we are still dismantling parts from the centre section. We have also continued working inside the tunnel, digging out large quantities of a curious mixed mass. What this mass is actually made up of is not easy to describe in a few words. Much of it is probably bottom sediment, mixed with various remains of equipment and types of corrosion products, salts, and also something with a consistency reminiscent of fine gravel.

Here there is nothing for it but to take one frame at a time and dig it all out by hand. It is exciting in its own way: in among all the «muck» we find various placards and so on, which are often in good condition.

Most of the equipment that was fitted inside the tunnel is sadly in poor condition. But it is exciting to see what, and how much, equipment was actually located here.

All posts in the He 115 diary · Heinkel He 115B · Flyhistorisk Museum Sola