28 May 2019
· Centre section, Methods and techniques
In the time since the last status update on the website, we have sealed the parts of the end walls of the Heinkel hall that are clad with timber boarding. The use of a dehumidifier inside the concrete hall caused this timber cladding to dry out, opening up all the gaps that had formed in the boarding so that moisture could migrate through them. As a result, the weather outside the hall had a considerable effect on the humidity inside it. We can now measure that the relative humidity inside the storage hall is both clearly more stable and clearly lower.
It is now summer and holiday time, and this will affect activity around the Heinkel He 115 project for a while.
Work has also continued both on the aircraft's instruments and on making copies of the brackets and mountings for the rudder pedals. The latter will be used as plugs in casting moulds.
The main priority of the Heinkel He 115 project is to preserve the aircraft as intact and untouched as possible. Nevertheless, it is a fact that the aircraft lay on the bottom of a fjord for 70 years, so salt has worked its way in between the aircraft's many joints. Our challenge is therefore still to find a method that best balances the wish to intervene as little as possible in the aircraft with the need to make sure the aircraft does not deteriorate over time. We are therefore still actively searching across a wide range of options to find it. At one end of this range is the possibility of electrochemical desalination, while at the other end is the possibility of dismantling the aircraft's parts wholly or partly. The aircraft's centre section is a complex structure with many very tight joints, so it will be difficult to remove the salt from these joints. As part of the investigation into the choice of method, we have recently spent some time mapping how the centre section is actually built. The aim is to get an overview of how it could be dismantled, either completely or piece by piece.
Since January 2018 work on the Heinkel He 115 project has been hampered because Forsvarsmuseet (the Norwegian Armed Forces Museum) is in the middle of a process to assess the future ownership of equipment on loan under deposit agreements. It now appears that this process has come far enough that the restrictions imposed on work on the aircraft may soon be lifted.
All posts in the He 115 diary · Heinkel He 115B · Flyhistorisk Museum Sola