25 December 2024
The autumn of 2024 has been a period in which a great deal has happened. We now have several activities going on at the same time, with good progress.
Good progress has been made on refitting parts that were removed from the nose and cockpit sections in 2014. Much work remains, but we are approaching the point where the original equipment we have is back in place in the two sections. The aircraft's control column and the elevator trim system still have to be rebuilt. Fortunately we have remaining parts of these two components that we can use in this work. The pilot's seat has been completely rebuilt from the remaining original parts and is now ready to be refitted in the cockpit. Work is now going on to rebuild what there was of the hydraulic system in the nose and cockpit. This is being done by combining the original pipes and couplings we have with newly made replacements for what is missing.


We have now finally got started on repairing the corrosion damage to the centre section's engine, float and wing mountings. Ahead of this work we spent time building a `bed` for the section to lie in while the repairs are under way. We have built jigs to ensure that the wing attachment fittings are refitted in the correct position. These are built so that one of the four wing attachment fittings can be loosened while the other three hold the structure stable in position. One jig has been built for each end of the centre section. The high demands on the accuracy of the jigs meant that building them cost us a great deal of time and work.


We have now drilled out and removed the first of eight wing attachment fittings.



The wing attachment fitting that was removed was placed in an electrolysis bath for two days. The result of this treatment is very good.


We have gained a good deal of experience along the way. We have found corrosion where we expected to find corrosion. At the same time we have opened up tightly riveted plates where the joints are completely undamaged. We cannot yet say for certain what explains the absence of salt and corrosion in these joints. Most probably the explanation has three parts.
- The aluminium used is seawater-resistant.
- The surface treatment was of high quality.
- The plates were coated with a `liquid` sealing compound before they were riveted together
This last point may have produced a tight joint that has been able to withstand 70 years of exposure to seawater. The explanation may also be different, and the condition of other joints need not be as good.
We hope to be able to conserve large parts of the centre section without having to open a large number of plate joints. A study has therefore been started under the auspices of Museums Spesialistene, a centre of expertise that provides advice and services to a number of museums in the region. The aim of the study is to find the best possible method of preventing corrosion from developing in joints. The centre section consists of a large number of riveted plate joints. These lay submerged in salt water for 70 years. It must be assumed that capillary forces have caused salt to migrate into them. Large parts of the centre section show few visible signs of corrosion. If we succeed in our aim, this could, on a world scale, be a distinctive way of preserving the originality of a wreck recovered from the sea.
The work on the centre section is being carried out in what was originally the tank in which the aircraft was stored submerged in fresh water for its first two years. Now that it is winter, the concrete structure acts as a cold accumulator. This, together with a dehumidified atmosphere, makes for a demanding working environment.