5 August 2026
· Nose and cockpit, Centre section
Through the winter and spring of 2026 we have continued the work of repairing corrosion damage around the wing attachment fittings on the centre section.
The work on the starboard front corner is now finished. We are carrying the experience gained there over to the work on the other three corners, which are now being worked on at the same time.
On the starboard rear corner the work has only just begun. Here we have started removing the float mounting.
On the port rear corner we have cut out the damaged piece of the web. Here we are once again faced with the same problem we had on the port front corner. It is not possible to replace the removed piece of plate with a plate identical to the one that was cut out, because there is no way of inserting it down and up into the gaps between the wing attachment fittings and the spars. The solution we have chosen is a recognised one within the aviation industry. It consists of using thinner plates of a higher-grade material. The plates are split in two in the horizontal plane to make it easier to get them into place down and up in the gaps. A plate of the same grade as the one used when the aircraft was built is then riveted on over these plates.





On the port front corner the web is now almost fully repaired and the float mounting has been refitted.

Considering that the aircraft lay in seawater for 70 years, the corrosion damage to the centre section is astonishingly slight. Even so, there is corrosion that must be dealt with beyond the obvious damage around the wing attachment fittings. This is mainly corrosion inside the MG 17 compartments. This damage will not directly reduce the structural strength of the aircraft, but it still has to be treated. We have not yet decided how this is to be done.
A good deal of work has also been done on the glazing above and in front of the pilot. The glazed roof above the pilot, with its rails and pulleys, came up with the aircraft when it was raised in 2012. After the glass had been cleaned and some repair work done on the rails, it has now been refitted over the cockpit. The windscreen in front of the pilot, with its frames, was missing entirely when the aircraft was raised. The frames have now been reconstructed, new Plexiglas panes have been made, and the whole assembly has been fitted.



The hood is also beginning to take shape. The wooden structure has been reconstructed and what remained of the original hood has now been integrated into it. New Plexiglas panes are being made as we go, and new aluminium strips are being made and screwed on to secure the glazing. A new hatch with hinges over the wireless operator's position still has to be made.


At the front, on the Kanzel section, the hatch over the gunner is finished and fitted. Work is still going on with the complicated reconstruction of the glazed housing over the navigator's seat. The work is very demanding, since there are neither drawings nor really good photographs of this structure. What makes it harder still is that the photographs we do have show that the aircraft were delivered with a number of different designs for this glazed housing. After first building the frames from aluminium tube, we have now chosen to make them from aluminium flat bar instead. These are now nearly ready to be welded together.



All posts in the He 115 diary · Heinkel He 115B · Flyhistorisk Museum Sola